-
Arrange for temporary electric service to the site and a portable
toilet if needed.
-
Stake out the house in preparation for the excavating as well
as utilities and a
temporary driveway if needed.
-
Remove any trees, bushes or debris as necessary from the
homebuilding site. Have the excavator cut down the grade if required.
-
Verify when your excavator will complete digging the
basement and
arrange for the footings and foundation walls to be poured immediately
after. Forms for footings must be inspected before pouring. If you leave the
empty hole standing, it will invariably cave in and you will have to start
over.
-
If you are going with a septic system, install a sleeve
for the sewer into the foundation wall. Likewise for any other openings you
may require. Make sure gas, electric and telephone arrangements have been
made and the trench for same dug.
-
You can install the septic system before the foundation,
simply do not excavate the basement until it is almost complete.
-
Once the footings and foundation walls have been poured,
install any steel beams required in the basement,
install drain tile and apply waterproofing to the exterior of the walls.
-
Begin drilling the well maintaining the distance from the septic
system that code dictates.
-
Allow 28 days for the
concrete to cure and then backfill. If you do not want to wait
for the concrete to fully cure you should install the first floor
framing, including sub-floor, before backfilling to brace the walls and keep them from cracking
under the pressure.
-
Frame the floors, walls,
ceilings and roof, including the 3/4" sub-flooring and the wall and
roof sheathing at this time.
-
Install the roofing and then house wrap, followed by the
soffit and fascia.
-
At this point you can begin the rough plumbing while
installing windows, exterior doors and siding and/or brick.
-
Build any masonry chimneys and fireplaces at the same
time.
-
Heat ducts should be installed immediately after the
rough plumbing. The same contractor may also install the gutters at this
point.
-
Rough in the electric.
-
Once the roof is on, windows in, rough plumbing done, and
inspected, with sewer and water lines run into the basement you can pour the
concrete
basement and garage floors. Also any concrete stoops or A/C pads required.
-
Do not forget all rough inspections must be complete
before you cover any interior walls.
-
Insulation, may have to be inspected in some localities.
-
Drywall installation, taping and sanding, and spray with
primer.
-
Install underlayment, ceramic tile and hardwood flooring.
-
Install cabinets, trim, accessories and built in
appliances.
-
Finish plumbing, electrical, (install fixtures), and install furnace and A/C.
Hook up telephone service.
-
Rough landscaping, if not already done with backfill, culverts, sidewalks and the driveway
can be completed now as most delivery trucks have come and gone.
-
Painting, staining and final inspections.
-
Finish landscaping (top soil, sod, seed etc.).
-
Carpet, linoleum and vinyl tile.
-
Final cleaning and move in!